
Code Powers under the UK Electronic Communications Code
Access to public and private land for Communications Providers
What are Code Powers?
Code Powers are statutory rights that allow an operator to install, maintain and operate electronic communications networks on land. These rights derive from the Electronic Communications Code under section 106 of the Communications Act 2003, as substituted by Schedule 1 to the Digital Economy Act 2017 (inserting Schedule 3A to the Communications Act 2003). Code Powers are not automatic. An operator must first apply to Ofcom for Code operator status, demonstrating financial capability, operational competence and technical compliance. Only once Ofcom confers Code Powers does the operator have the statutory right to seek land access for network deployment.
The Electronic Communications Code framework balances two competing interests. Network operators need reliable access to land at predictable cost to build the infrastructure that underpins digital services. Landowners need protection against unreasonable intrusion on their property rights and fair compensation for any loss or diminution in value caused by the network installation. The Code creates a structured process for negotiating that balance, with the tribunal as the arbiter when negotiation fails.
Who can obtain Code Powers?
Code Powers are available to persons providing an electronic communications network or a system of infrastructure made available to providers of such networks. This includes mobile network operators, fibre network operators, and neutral-host infrastructure companies. In practice, any person who needs statutory access to land for the deployment of electronic communications apparatus may apply.
Ofcom assesses Code applications against statutory criteria. These include fitness and propriety of the applicant, financial resources adequate to meet Code liabilities, operational plans for network deployment and maintenance, and evidence of effective compliance arrangements. Ofcom maintains a public register of Code operators showing those to whom Code Powers have been conferred. Code Powers are not granted to operators for purely private networks used solely for internal purposes; such networks typically rely on contractual land rights negotiated separately.
Tower companies, subsea cable operators, wireless ISP providers and new entrant fibre operators all hold Code Powers in practice. Code Powers bind the operator to statutory obligations to landowners and to the public. These include bonding or financial security to cover statutory liabilities for the statutory liability period, typically set during construction as a percentage of construction costs and thereafter by reference to annual operations and maintenance costs. An operator that loses Code Powers or fails to maintain required bonding faces enforcement action from Ofcom and may be unable to enforce existing Code agreements.
The section 106 application process
An applicant seeking Code Powers must submit a formal application to Ofcom under section 106(3) of the Communications Act 2003. Ofcom publishes notification of the application and typically opens a consultation period, usually of 28 days, during which third parties may submit representations. This consultation allows existing operators and other stakeholders to lodge concerns about the new applicant’s financial strength, operational capability or compliance record.
Ofcom will assess the application against the statutory criteria and issue a decision. If approved, Ofcom will issue a direction conferring Code Powers. The conferral of Code Powers may be subject to conditions or restrictions imposed by Ofcom under the Electronic Communications Code (Conditions and Restrictions) Regulations 2003. Common conditions include minimum levels of financial security, regular reporting of compliance, and obligations to share duct or pole infrastructure with other operators.
The section 106 process typically takes between six and nine months from application to final direction. Applicants should budget for this timeline and factor it into network deployment schedules. Once Ofcom issues a direction, the conferral can be challenged by judicial review if the decision is irrational or procedurally defective; otherwise, the applicant has Code Powers for so long as it complies with the conditions attached.
The practical exercise of Code Powers: Negotiation and notices
Once an operator holds Code Powers, it may exercise those rights by negotiating Code agreements with landowners or, if negotiation fails, by serving statutory notices and seeking a Code order from the tribunal. In practice, most operators prefer negotiation. A negotiated agreement is usually cheaper, faster and more stable than tribunal proceedings, and avoids the public and reputational cost of formal dispute.
The negotiation process begins with notice. The operator must serve notice on the landowner setting out the proposed apparatus, the land to be used, the intended use and duration, and the financial terms proposed. The notice must comply with Part 3 of Schedule 3A, which sets out the form and content required. The notice must state the landowner’s right to object or propose alternative terms and set out statutory timeframes for response, typically 28 days or such longer period as the parties agree.
The tribunal case law has established strict technical requirements for notices. A notice that fails to comply with the statutory form or that fails to disclose material aspects of the operator’s network plans or the financial basis of the proposal may be treated as invalid by the tribunal. Operators that rush notice service often discover that their notices are defective and must be re-served, causing delay. Experienced advisors draft notices with precision and review them against tribunal precedent.
During the negotiation phase, landowners should take independent legal and valuation advice before responding to a notice. The response sets the tone for negotiation and the quality of the response determines the landowner’s negotiating position. A poorly drafted response that fails to identify specific objections or to propose realistic counter-terms weakens the landowner’s position if the dispute later goes to tribunal.
Paragraph 20 and the tribunal route
Paragraph 20 of Schedule 3A sets out the conditions under which an operator may impose a Code agreement on a non-consenting landowner by applying to the First-tier Tribunal (Property Chamber). The operator must demonstrate three things: first, that it has made a genuine attempt to secure the landowner’s agreement on reasonable commercial terms; second, that the landowner’s refusal is unreasonable; and third, that the benefit to the public of network coverage and competition outweighs the landowner’s loss.
Jurisdiction over Code disputes in England and Wales transferred from the Upper Tribunal (Lands Chamber) to the First-tier Tribunal (Property Chamber) on 6 April 2024 under the Electronic Communications Code (Jurisdiction) (Amendment) Regulations 2023 (SI 2023/1220). Case law developed by the Upper Tribunal remains authoritative and is applied by the First-tier Tribunal.
The tribunal does not automatically grant a Code order simply because these conditions are technically met. The tribunal will examine the merits of the operator’s proposal in detail, assess the strength of the public benefit case, and consider whether the landowner’s objections are well-founded or merely obstructive. Many operators that assume Code rights are automatic discover when they apply to the tribunal that they cannot meet the paragraph 20 threshold without further negotiation or technical modifications to their proposal.
The First-tier Tribunal (Property Chamber) now has jurisdiction over all paragraph 20 proceedings in England and Wales following amendments made by The Electronic Communications Code (Jurisdiction) (Amendment) Regulations 2023. The tribunal will hear oral evidence, including expert evidence on valuation and technical evidence on network design and feasibility. The tribunal decisions are binding on parties and establish precedent for future cases.
Valuation of Code agreements: the no-scheme basis
One of the most consequential reforms introduced by the 2017 Digital Economy Act was a change to the valuation basis for Code agreements. Before 2017, operators typically paid wayleave agreements valued on the basis of open market value, reflecting what a willing buyer and seller would agree if the Code did not exist. The 2017 reforms substituted a “no-scheme” valuation basis, which fundamentally reduces the compensation payable to landowners.
The Code now requires compensation to reflect the loss or diminution in value of the landowner’s land caused by the operator’s installation, not the hypothetical value of the land if the network did not exist. The tribunal has consistently held that landowners are not entitled to share in the benefits created by network coverage. Compensation is calculated by expert evidence reflecting the loss of use, impact on rental value, impact on future development or sale value, and cost of reinstatement. Comparable evidence of other telecoms transactions is not admissible for valuation purposes under the no-scheme approach.
For operators, this represents a substantial reduction in the cost of securing land access. For landowners, it represents a loss of income compared to the pre-2017 market-value wayleave model. Many landowners still believe they are entitled to market value compensation and refuse to accept Code agreements on no-scheme terms. This belief is incorrect and often leads to costly tribunal disputes that the landowner will lose on the law. Advisors representing landowners must explain this clearly and early to manage client expectations.
The PSTI Act 2022 reforms: interim rights and consideration
The Product Security and Telecommunications Infrastructure Act 2022 introduced substantial amendments to the Electronic Communications Code, with key provisions taking effect on an ongoing basis. These reforms were designed to support faster broadband and 5G rollout by giving operators additional statutory tools and by clarifying landowner protections.
One important innovation is the expansion of interim rights. Previously, Part 5 of Schedule 3A allowed only landowners to apply to the tribunal for interim changes to consideration pending final determination of a Code agreement renewal application. The PSTI Act 2022 now permits either party to apply for interim relief, including changes to financial terms, with effect backdated to the date of application. This creates new tactical opportunities for both operators and landowners in renewal negotiations.
The PSTI Act also clarified the automatic renewal rights of operators. An operator that fails to secure a renewal agreement before the existing Code agreement expires may rely on the Code’s automatic renewal provisions to continue operating on the same terms pending final determination of a new agreement. This protection prevents operators from losing Code rights through administrative oversight and provides breathing space for negotiation or tribunal proceedings. The practical effect is that expiring Code agreements rarely lead to immediate loss of access.
Towercos and Code Powers
Tower companies that provide shared site infrastructure to multiple MNOs hold Code Powers in the same way as operators building their own networks. The Code applies to towercos with no qualification or exemption. A towerco that provides duct or pole access to MNOs may need Code rights to secure access to the properties where the shared infrastructure is located.
In practice, towercos often exercise Code Powers alongside contractual rights. A towerco may have a contractual right to install a tower at a particular location, with that right derived from a ground lease or similar arrangement, and may also seek Code operator status to ensure it has statutory backing for the exercise of those rights. The combination of contractual and statutory rights provides security against future disputes with landowners.
Code Powers and planning permission
A critical area of confusion in practice concerns the relationship between Code Powers and planning permission. These are separate regulatory regimes with different decision-makers and different purposes. An operator may have valid Code rights to install apparatus but still require planning consent. Conversely, planning permission does not confer Code rights: an operator that has obtained planning permission for a tower at a particular location still needs either the landowner’s agreement or a Code order to exercise Code rights over the land.
Getting the sequencing right at the outset is critical. Some operators apply for planning permission first, then serve Code notices. Others serve Code notices first, then apply for planning permission. There is no universal “correct” sequence; the optimal sequence depends on the specific project. But an operator that neglects planning permission or that underestimates the planning risks faces project delay and cost. Planning authorities have rejected proposals that had underlying Code rights, forcing operators to modify their network design or abandon locations. The cost of rework can be substantial.
An operator should take early planning advice on the specific location and proposed apparatus type. Some apparatus types (such as small cells on existing poles) may be permitted development under planning rules and require no formal consent. Others require full planning permission. Some locations have local planning constraints or conservation area designations that create risk. A conversation with the local planning authority at the outset, before Code notices are served, can save months of rework.
Wayleave agreements versus Code agreements
Wayleave agreements predate the Code. They are voluntary agreements between an operator and a landowner for the installation of apparatus, typically granted on an annual or renewable basis and terminable by notice. A wayleave gives the operator no statutory rights; if the landowner refuses to grant a wayleave or terminates an existing wayleave, the operator has no override.
Code agreements, by contrast, are statutory agreements that an operator can impose on a non-consenting landowner by tribunal order under paragraph 20. Most new network builds use Code agreements as the legal basis for infrastructure access, particularly where the operator anticipates possible landowner objections or where the land is geographically strategic and the operator does not want to be dependent on the landowner’s continued consent.
In practice, operators often continue to use wayleave agreements for locations where negotiation is straightforward and the operator has a good relationship with the landowner. Wayleaves may be faster to negotiate than Code agreements because they avoid formal notice procedures. But a landowner can terminate a wayleave; an operator with a Code agreement cannot be removed by the landowner (though the landowner can apply to the tribunal for termination on the Code’s terms).
The valuation methodology differs. Wayleaves are typically valued on a market basis; Code agreements on a no-scheme basis. This creates an incentive for operators to push existing wayleave holders toward Code agreements where the operator can demonstrate that the Code agreement value (on a no-scheme basis) is lower than the wayleave rent. Some landowners resist this conversion and defend their existing wayleaves. Disputes over conversion often go to tribunal where the operator seeks a Code order to replace the wayleave.
Practical triggers for instructing legal advice
Operators should instruct Code advice at the earliest stage of network planning, before Code notices are served. Early advice on application for Code operator status, on the requirements for compliant notices, and on the sequence of Code and planning processes will save cost and delay.
Landowners receiving Code notices should instruct immediately. Code notices establish statutory timeframes for response, and the quality of the response determines the landowner’s negotiating position. A landowner that fails to respond within the statutory period loses important protections.
Operators that have served Code notices and received landowner objections should instruct before escalating to paragraph 20 proceedings. Paragraph 20 proceedings are expensive and carry material risk of tribunal judgment against the operator if the tribunal finds that the operator has not made a genuine attempt to reach agreement or that the public benefit case is weak.
Acquisition due diligence on land with existing Code agreements should always include legal review. The commercial value of land depends entirely on the scope and duration of the operator’s Code rights. An acquiring party that does not understand the Code agreement, and the circumstances under which the operator can compel variation or renewal, may discover post-acquisition that ownership comes with material restrictions on use.
Code disputes involving upgrades, technology migrations or shared infrastructure arrangements require specific advice on whether existing Code rights cover the proposed works or whether fresh Code negotiations are required. An operator that assumes existing rights cover new apparatus types or new use cases often discovers that it needs fresh Code agreements, requiring re-negotiation or tribunal application.
Tribunal case law and its practical importance
Since 2017, the First-tier Tribunal (Property Chamber) has developed a substantial body of precedent on the Code. This case law addresses technical compliance (what constitutes a valid notice, what the operator must disclose, what the tribunal will infer from defective procedure), valuation methodology (how to apply the no-scheme basis, what evidence the tribunal will accept, how to approach shared access arrangements), and the paragraph 20 threshold (what counts as “genuine attempt to reach agreement”, what “unreasonableness” means, how the tribunal balances public benefit against landowner loss).
Any negotiation of Code rights now demands engagement with this jurisprudence. The Code itself is a framework; the case law fills in the details. Disputes over valuation, notice compliance, the scope of Code rights, and the grounds for tribunal intervention are ultimately resolved by reference to precedent. Operators and landowners that ignore the case law find themselves making arguments that the tribunal has already rejected in earlier decisions.
Case law knowledge is particularly important in valuation. The tribunal has given detailed guidance on valuation methodology, the types of evidence it will and will not accept, and how to approach particular scenarios (such as shared access arrangements or upgrades to existing installations). This guidance materially affects the commercial position of both operator and landowner and should shape negotiating strategy.
Bonding and financial security requirements
An operator holding Code Powers must maintain a bond or financial guarantee covering its statutory liabilities to landowners and the public. The quantum of bonding is typically set by Ofcom in the direction conferring Code Powers. During construction, bonding is often set as a percentage of construction costs (typically 10-20%). Once the network is operational, bonding shifts to an assessment of annual operations and maintenance costs. An operator that fails to maintain required bonding is in breach of its Code Powers and faces enforcement from Ofcom and potential claims from landowners.
Bonding arrangements are material to financing and investment. Financiers and investors will assess the bonding burden as part of due diligence. An operator that underestimates bonding requirements or that fails to budget for ongoing bonding costs may face financial stress. Conversely, a landowner considering enforcement against an operator can assess whether the operator’s bonding is sufficient to cover the landowner’s potential claims.
FAQs
What is the difference between a wayleave and a Code agreement?
Wayleaves predate the Electronic Communications Code. They are agreements between an operator and a landowner for the installation of apparatus, typically granted on an annual or renewable basis and terminable by notice. A wayleave is a voluntary agreement; the landowner can refuse to grant one and the operator has no statutory override. When the Communications Act 2003 introduced the Code regime, it added a statutory mechanism (paragraph 20) for imposing Code agreements on non-consenting landowners. In practice, most operators still use wayleaves for new installations where they can negotiate agreement; Code agreements become relevant where negotiation fails or where an existing wayleave is being replaced. The valuation methodology is different: wayleaves are typically valued on a market basis; Code agreements on a no-scheme basis.
Can an operator compel me to accept a Code agreement without my consent?
Yes, but only if the operator meets the conditions in paragraph 20 of Schedule 3A. The operator must have made a reasonable attempt to secure your agreement; your refusal must be unreasonable; and the benefit to the public of network coverage and competition must outweigh your loss. If the operator can satisfy these conditions, it can apply to the First-tier Tribunal (Property Chamber) for a Code order imposing the agreement. This is not automatic; the Tribunal will examine the operator’s proposal and your objections. Many operators do not pursue paragraph 20 if they cannot make a compelling case for public benefit.
How is the compensation for a Code agreement calculated?
The Code requires compensation to reflect the loss or diminution in value of your land caused by the operator’s installation. The tribunal case law has established that this is a “no-scheme” valuation: the compensation reflects the value of your land without the operator’s network, not the value if the network did not exist. Relevant losses include loss of use of the land, impact on its rental value, impact on future sale value if the installation restricts future development or use, and cost of reinstatement. The compensation does not include notional value from network coverage. Valuation is typically determined by expert evidence.
What happens if my Code agreement expires or the operator wants to upgrade the installation?
If the agreement expires, the operator can either seek your agreement for renewal on the same or different terms, or apply to the First-tier Tribunal (Property Chamber) under paragraph 20 if you refuse. If the operator wants to upgrade the installation, the treatment depends on the scope of the upgrade. A minor upgrade (replacing existing apparatus with similar apparatus) may be achievable within the existing Code agreement. A material upgrade (increasing the footprint, adding new apparatus types, or changing the installation’s character) typically requires fresh Code rights negotiation, as though the operator were installing apparatus for the first time.
Can a Code agreement restrict my use of my own land?
Yes. A Code agreement confers rights of access, installation and maintenance on the operator. The agreement will specify the area over which the operator has rights and may restrict your use of that land. You cannot use the land in a way that interferes with the operator’s rights or damages its apparatus. However, the Code regime permits you to continue ordinary use of the land if it does not interfere with the installation. Disputes often turn on what “ordinary use” means in the context of the specific land.
Need Code Powers support?
Representative experience
Recent and representative matters include:
- Advised a national fibre operator on the exercise of Code rights under the reformed Electronic Communications Code, including paragraph 20 agreements for multi-dwelling unit access.
- Negotiated wayleave and access agreements for a subsea cable operator’s landing station and terrestrial route, addressing Code rights, planning consents and landowner objections.
- Supported a tower company in a portfolio of Code agreement renewals following the Digital Economy Act 2017 valuation reforms, including contested “no-network” site value assessments.
- Advised a property developer on the interaction between Code operator rights and development lease covenants, including the scope of paragraph 27 (apparatus removal) obligations.
- Acted for a rural broadband provider in securing access to highway land and agricultural crossings under the Code, coordinating with Highways England and local authorities.
Related telecoms regulation pages
See also our other telecoms regulation pages:
- Interconnection regulation
- Ofcom General conditions of entitlement
- Numbering
- Spectrum
- Lawful intercept and the Investigatory Powers Act 2016
- Ofcom Licence Fees
- Am I regulated?
- SMP regulation and market reviews
- Telecoms Security
- Ofcom
- Complaints and investigations
- Connected Vehicles and IoT Regulation
Why Choose Bratby Law?
Sector expertise
Bratby Law advises exclusively on telecoms regulation, data protection, and payments regulation. That concentration means deeper knowledge of the regulatory environment, faster analysis, and advice that reflects how regulators actually behave: not how the textbook says they should.
Senior delivery
Every instruction is handled by Rob Bratby personally. With 30 years’ experience spanning Oftel, senior in-house roles at network operators, and partnership at international law firms, you receive the analysis directly: not through a junior team. The firm uses AI tools to extend research capacity and accelerate document review, so senior judgment is applied to more of your matter, not less.
Unique perspective
Rob Bratby has sat on all three sides of the regulatory table: as a regulator at Oftel, as General Counsel at major operators, and as external counsel. That inside-out perspective informs every piece of advice. He currently holds fractional General Counsel appointments at TOTSCo, UKPI, TelXL, and Core.
Independent directory rankings
Our specialist expertise is recognised in major independent legal directories:
- Chambers & Partners: Rob Bratby is ranked as a band 2 lawyer in the UK Guide 2026 in the “Telecommunications” category: Chambers
- The Legal 500: Rob Bratby is listed as a “Leading Partner – Telecoms” in London (TMT – IT & Telecoms): The Legal 500
- Lexology: Rob Bratby is featured on Lexology’s expert profiles as a Global Elite Thought Leader for data: Lexology



What clients say about Bratby Law:
Related Services
- Why Bratby Law? UK Telecoms Lawyers and AI Lawyers for Regulated Markets
- Services
- Am I Regulated?
- General Conditions of Entitlement
- Interconnection and Access Agreements
- Digital Infrastructure Projects
- Fractional General Counsel
- Transactions
- Co-counsel
See also: Network sharing and co-location agreements and Subsea cables.
Frequently asked questions
What are Code Powers?
Code Powers are statutory rights granted by Ofcom under Schedule 3A to the Communications Act 2003, enabling operators to install, maintain and operate electronic communications networks on land.
Do I need Code Powers to deploy a fibre or mobile network?
Yes, where deployment requires access to land or public highways and the network is provided to external parties.
Do neutral-host or wholesale providers require Code Powers?
Yes. Providers offering infrastructure to third parties typically require Code Powers if they need access to public or private land.
Do private or campus networks require Code Powers?
Not usually. Private networks used solely for internal purposes may rely on contractual land rights.
How does Ofcom assess a Code Powers application?
By assessing fitness and propriety, financial resources, operational plans and compliance arrangements.
What bonding or guarantee is required for Code Powers?
Operators must maintain a bond or guarantee covering liabilities to landowners and the public for the statutory liability period. During construction, this is typically set as a % of the construction costs, thereafter by reference to annual operations and maintenance costs.
How do Code upgrade and sharing rights work?
Operators have statutory rights to upgrade or share apparatus subject to conditions, without needing landowner consent.
What happens if agreement with a landowner cannot be reached?
Operators may seek a Code agreement through the First-tier Tribunal (Property Chamber).
What liabilities do Code operators have when apparatus is removed?
Liabilities include reinstatement obligations and compensation for loss or damage.
How do Code Powers affect transactions or financing?
Investors assess Code compliance, bonding arrangements and the enforceability of land access rights as part of due diligence.

